Data Center Expansion Commissioning

We commissioned the critical infrastructure for a major US telecom provider’s 78,000 sq. ft. data center expansion.

 

End of Life Equipment Replacement Commissioning

We assisted in the seamless transition to new electrical and mechanical infrastructure supporting 3.75MW of critical load for a major Canadian financial institutions' data center.

 

Data Center Expansion Commissioning

We commissioned the critical infrastructure for an 8,000 sq. ft. data center expansion for a major US colocation provider.

1
1

Critical Facilities Commissioning

Critical Facilities Commissioning

Commissioning is a separate and distinct quality assurance process that starts during design and continues through construction, occupancy, and operations. Commissioning ensures that on Day 1 the new building operates as the owner intended and that the building staff is sufficiently prepared to operate and maintain its systems and equipment.

Our dedicated, experienced teams can provide full commissioning services for data centers or other critical facilities anywhere in North America.

  • Building Envelope Commissioning
  • Emergency Operating Procedures
  • Equipment and Component Testing
  • Factory Witness Testing
  • Functional Testing
  • Integrated Systems Testing
  • Methods of Procedures
  • Operational Review
  • Peer Review
  • Retro Commissioning
  • Seasonal and Warranty Review
  • Standard Operating Procedures
  • Systems Training

Contact Our Team

Read the Latest From Our Blog on Commissioning Critical Facilities

The Most Important Data Center Design and Infrastructure Codes and Standards

Posted on Wednesday January 27, 2016

Sorting through the applicable codes and standards to identify, design, and build your data center tailored to your company needs can be a daunting process... Read More »

Presentation: What is Mission Critical Commissioning and Why is it Critical?

Posted on Monday April 27, 2015

This presentation by Mission Critical Practice Lead Steven Shapiro, P.E. was given at Data Center World in April, 2015. It explains the need for mission critical commissioning for critical environment as well as what types.. Read More »

Steven Shapiro to Speak Next Week on Myths of Data Centers and Why Mission Critical Commissioning is Critical

Posted on Wednesday April 15, 2015

“Most organizations still believe some very common myths about Tier Ratings and high availability data centers, and I’m looking forward to sharing our insight,” said Mr. Shapiro, who has over 26 years of experience in.. Read More »